Current and Pending Projects in Central Pool Classrooms

During the the winter, spring, and summer of 2010, the Classroom Facilities Review Committee and Classroom Technology Services plan to improve 26 classrooms in the Central Pool. The new Music Building addition will also include three classrooms that will be incorporated into the Central Pool. We anticipate the addition of these classrooms in time for the Spring 2010 term.

For additional information, please contact Jeff Douthett, Manager of Classroom Technology Services (douthett@isc.upenn.edu).

Please note that these classrooms will not be available for use for academic or special events at any time on the dates between the start date and the expected completion date (inclusive).

Building Classroom Description of Work Start Date Expected Completion Status
Fisher-Bennett Hall 11 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 12 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 13 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 15 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 16 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 17 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 19 projector replacement
removal of VCR
August 21, 2010 August 28, 2010 pending
Fisher-Bennett Hall 20 projector replacement
removal of VCR
August 21, 2010 August 28, 2010 pending
Fisher-Bennett Hall 24 projector replacement
removal of VCR
August 21, 2010 August 28, 2010 pending
Fisher-Bennett Hall 25 projector replacement
removal of VCR
August 21, 2010 August 28, 2010 pending
Fisher-Bennett Hall 29 projector replacement
removal of VCR
June 19, 2010 June 26, 2010 pending
Fisher-Bennett Hall 138 projector replacement
removal of VCR
January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 139 projector replacement
removal of VCR
January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 140 projector replacement
removal of VCR
January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 141 projector replacement
removal of VCR
January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 201 projector replacement
removal of one VCR
(second VCR to be retained)
July 6, 2010 September 3, 2010 pending
Fisher-Bennett Hall 222 projector replacement
removal of VCR
July 6, 2010 September 3, 2010 pending
Fisher-Bennett Hall 224 projector replacement
removal of VCR
July 6, 2010 September 3, 2010 pending
Fisher-Bennett Hall 231 projector replacement
removal of VCR
July 6, 2010 September 3, 2010 pending
Fisher-Bennett Hall 244 projector replacement
removal of one VCR
(second VCR to be retained)
July 6, 2010 September 3, 2010 pending
Fisher-Bennett Hall 322 removal of VCR January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 322 projector replacement March 6, 2010 March 14, 2010 pending
Fisher-Bennett Hall 323 removal of VCR January 4, 2010 January 13, 2010 pending
Fisher-Bennett Hall 323 projector replacement March 6, 2010 March 14, 2010 pending
Fisher-Bennett Hall 401 projector replacement
removal of one VCR
(second VCR to be retained)
May 18, 2010 July 2, 2010 pending
Fisher-Bennett Hall 406 projector replacement
removal of VCR
May 18, 2010 July 2, 2010 pending
Fisher-Bennett Hall 407 projector replacement
removal of VCR
May 18, 2010 July 2, 2010 pending
Fisher-Bennett Hall 419 projector replacement
removal of VCR
May 18, 2010 July 2, 2010 pending
Leidy Lab 10 projector replacement January 4, 2010 January 12, 2010 pending

Last Update: November 3, 2009